Looking forward: Jan. 14 -18
For the week ahead, crews are scheduled to: finish the installation of sidewalks, curbs and curb ramps along the 1300 block; finish the 13th Street storm drain inlet; begin crosswalk construction on the east side of 13th Street; demolish and replace sidewalks, curbs and curb ramps along the 1200 block. Construction activities are subject to change.