Feb. 11 - 15: 14th Street intersection closure
The T intersection at 14th Street and Camino del Mar is scheduled to close from 7 a.m. through 5 p.m. next week to allow for the installation of a paver crosswalk. The closure will affect the immediate work zone only. Maiden Lane and access to a parking garage on the northeast corner of the intersection will remain open.
A detour route will direct vehicles to 15th and 13th Streets. At the close of each workday, crews will lay steel plates over the crosswalks to reopen the intersection.
More paver crosswalk installations, at 13th and 12th streets, are scheduled for the week of Feb. 18 through Feb. 22. During this period, through-access will not be provided after work hours because of narrow roads and safety concerns. Detour routes will send vehicles to 14th and 11th streets.
Also for next week, demolition and concrete work is scheduled to continue on the 1200 and 1100 blocks of Camino del Mar.