The 1100 Block
Downtown Streetscape construction this week continued to concentrate on the east side of the 1100 block of Camino del Mar. Since the project began in January, the 1100 block has represented the most involved block so far, with new construction stretching from storefronts to the highway. Crews have built curbs, sidewalks, brickwork and drainage.
More of the same is scheduled for the week ahead, including construction of a retaining wall and pedestrian ramp at the northeast corner of Camino del Mar and 11th Street. Work on the 1100 block is scheduled to continue through the week of March 25 to complete the pedestrian ramp and paving of parking spaces.